Page 230 - UK Regulation Part 21 Initial Airworthiness Annex I (consolidated) March 2022
P. 230

PART 21 - INITIAL AIRWORTHINESS (ANNEX I)


                                                    -  A resume of at least the following subjects:
                                                    -  Changes in organisation and qualification of the subcontractor.(in case of
                                                      impact on the procurement),
                                                    -  Quality problems encountered during manufacture,
                                                    -  Corrective actions following problems encountered earlier on the
                                                      procurement,
                                                    -  Findings from national authorities surveillance that may have an impact on
                                                      the procurement,
                                                    -  Quality problems related to the contractor procurement (materials,
                                                      documentation, procedures, processes).
                                                  Exchange of information between national authorities according to this procedure is
                                                  strictly confidential and should not be disclosed to other parties.
                                                  It is recommended to plan at least every 5 years a meeting between Industry and
                                                  the two national authorities to review each major subcontract to verify proper
                                                  management by the various parties involved.
                                           3.  Miscellaneous
                                                   a)  Release documentation
                                                      Release of parts by the POA subcontractor to the contractor will be
                                                      accompanied by an «Authorised Release Certificate CAA Form 1» issued for
                                                      «Airworthiness» or for «Conformity» as appropriate.
                                                   b)  Sub-subcontracting
                                                      If the subcontractor wants itself to subcontract, it is up to the CAA of the
                                                      subcontractor to verify that this is done in accordance with the conditions of
                                                      the contract, to organise as necessary the related authority surveillance and
                                                      to inform the CAA of the contractor.
                                                   c)  Language
                                                      Except if agreed otherwise it is recommended to use the English language
                                                      for exchange of information between the competent authorities.


























































     March 2022                                                                                             230 of 260
   225   226   227   228   229   230   231   232   233   234   235