Page 35 - Performance / Statistics
P. 35

8. Increase in Sectional Speeds and New lines.

                   a.  Sectional Speeds

                     FM-DHNE Section – CRS sanction received for Raising of sectional speed from
                       100 to 110 Kmph on 02.12.2020 and implemented.

                     SHNR –GLY (New Double Line) – Line commissioned in the month of Sept‟20
                       with MPS 75 Kmph and PCE approval received for increasing speed from 75 to
                       100 Kmph on 03.02.2021, will be implemented by 31.02.2021.


                   b.  New Lines

                     Jaklair – Makthal - new line (11 Km) – Commissioned in the month of June‟20,
                       to be taken over by open line from construction.

                     Manoharabad – Gajwel - new line (33 Km) – Commissioned in the month of
                       June‟20, to be taken over by open line from construction.

                     Shadnagar – Gollapalli – Double line (DN Line) (30 Km) – Commissioned in
                       the month of Sept‟20, taken over by open line.




               9. Maintenance of service and residential buildings:

                     The following works were carried out during the year 2019-20 for
                       maintenance of staff quarters.

                                                                                  Target       Progress
                  Sl No                           Work
                                                                                 2020-21       (Feb‟21)
                     1      Directed maintenance of Buildings                       200           166

                     2      Repairs to leaky roofs of Quarters                      50            45
                     3      Provision of Pathways                                   50            45
                     4      Replacement of Doors & windows in Quarters              120           103

                     5      Provision of Mosquito Mesh in Quarters                  120           108

                 Rain water Harvesting:

                                      Target 2020-21                Progress  (Feb‟21)
                                             80                              78





                                                            133
   30   31   32   33   34   35   36   37   38   39   40