Page 35 - Performance / Statistics
P. 35
8. Increase in Sectional Speeds and New lines.
a. Sectional Speeds
FM-DHNE Section – CRS sanction received for Raising of sectional speed from
100 to 110 Kmph on 02.12.2020 and implemented.
SHNR –GLY (New Double Line) – Line commissioned in the month of Sept‟20
with MPS 75 Kmph and PCE approval received for increasing speed from 75 to
100 Kmph on 03.02.2021, will be implemented by 31.02.2021.
b. New Lines
Jaklair – Makthal - new line (11 Km) – Commissioned in the month of June‟20,
to be taken over by open line from construction.
Manoharabad – Gajwel - new line (33 Km) – Commissioned in the month of
June‟20, to be taken over by open line from construction.
Shadnagar – Gollapalli – Double line (DN Line) (30 Km) – Commissioned in
the month of Sept‟20, taken over by open line.
9. Maintenance of service and residential buildings:
The following works were carried out during the year 2019-20 for
maintenance of staff quarters.
Target Progress
Sl No Work
2020-21 (Feb‟21)
1 Directed maintenance of Buildings 200 166
2 Repairs to leaky roofs of Quarters 50 45
3 Provision of Pathways 50 45
4 Replacement of Doors & windows in Quarters 120 103
5 Provision of Mosquito Mesh in Quarters 120 108
Rain water Harvesting:
Target 2020-21 Progress (Feb‟21)
80 78