Page 33 - Performance / Statistics
P. 33
3. Track machine utilisation:
Progress up to
Sl No Type of Machine Target 2020-21
Feb‟21
1 Tie Tamping Machine 1300 Km 1466 Km
2 Unimat 500 Pts 478 Pts
3 BCM 80 Km 76.00 Km
4. Level crossing works
Elimination of Manned Level Crossings.
Progress
Sl Description of Boards Internal
No item Target Target up to Remarks
Feb 21
Construction of
1 - - - -
Road Over Bridge
LC No: 18,26, 44, 49, 109, 112,
Construction of
2 Limited Height 10 12 14 119, 140 on SC-DHNE section,
LC No: 245, 232, 230, 224,
Subways
213, 208 on SC-MUE section
Closure of Level
crossings on
3 - - - -
account of
diversion of Traffic
Closure of Level
crossings on
4 - - - -
account of meager
traffic
5. Relaxation of Permanent Speed Restrictions.
Target 2020-21 = 02
Progress = 02
Existing PSR
Remarks
Sl
No Km Section SR Reasons
218/0- IKI-MOA- Consolidation of
01 75 Kmph Relaxed in Jan‟2021
222/0 ALPR Track
491/0- 4 D curve in
02 UPW-SCP 60 Kmph Relaxed in Feb‟2021
492/0 Ghat section
131