Page 47 - Performance / Statistics
P. 47

  Afforestation

                                             Target                                   Actual
                              For the Month         Cumulative        For the Month         Cumulative
                Category
                             Route     No. of    Route      No. of    Route  No. of      Route       No. of
                               Km      Trees     Km/Ha      Trees      Km      Trees     Km/Ha       Trees
                Boundary
                Plantation    8.33     10000      91.63    110000       25     30000     150.00     180000
                  Block
                Plantation     15      15000       165     165000       10     10000     160.0      160000
                Miyawaki
                Plantation    0.27     8333.3     2.97      91666       0        0         0.3       10000

                     Rain Water Harvesting (No. of Stations)

                                  Target                        Actual
                                    80 os.                      78 Nos.


                     Energy Conservation

               Renewable Energy

                                       For the Month of      Cumulative for the
                       Item               Feb -2021           Year 2020-2021        For the Month of Feb -
                                                                                             2021
                                      Target      Actual      Target      Actual
               Renewable                                                              Field survey under
               Energy                300kWp          -       3000kWp        0          progress by M/s.
               Commissioned                                                                 REMCL
                                                                                     Under process at 11
               Energy Audits             1           0           1          0
                                                                                           Locations

                     Certification for Environment Management (ISO-14001) –

                    All the four nominated stations have obtained ISO certificates

                    1. KCG Railway Station achieved ISO 14001:2015 certificate.
                    2. KRNT Railway Station achieved ISO 14001:2015 certificate.
                    3. NZB Railway Station achieved ISO 14001:2015 certificate.
                    4. BSX Railway Station achieved ISO 14001:2015 certificate