Page 29 - GM Booklet 06.03.2021_Neat
P. 29
3. Progress of Through Rail Renewal (P) and Through Sleeper Renewal Works.
2020-21
Item Progress up to Remarks
Target
Feb 2021
1.04 Tkm Rails (20 RP)
TRR (P) 07 Km 5.93 Km received and unloaded on
23.02.2021.
TSR (P) 05 Km 05 Km Target achieved.
4. Reduction in Asset Failures
Rail / Weld failures - Division has achieved a reduction of 41 % over last year, In
the year 2020-21 Rail / Weld failures were 10 Nos compared to 17 Nos in the year
2019-20.
5. Relaxation of Permanent Speed Restrictions.
Target 2020-21 = 02
Progress = 02
Existing PSR
Remarks
Sl
No Km Section SR Reasons
218/0- IKI-MOA- Consolidation of
01 75 Kmph Relaxed in Jan‟2021
222/0 ALPR Track
491/0- 4 D curve in
02 UPW-SCP 60 Kmph Relaxed in Feb‟2021
492/0 Ghat section
6. Through formation Treatment with Moorum Blanketing: The work of Through
Formation Treatment is in progress on SC-MUE section and a progress of 7.910 Km has
been achieved.
20