Page 31 - GM Booklet 06.03.2021_Neat
P. 31
iii. BCM 290 machine, which is working in the Division is about 30 Yrs old machine. The
progress achieved by the machine is about 64 Km in 09 Months, which is the highest
ever progress in the History of working of BCM-290 machine.
iv. During lockdown period, when passenger carrying train traffic was less, the
opportunity of traffic blocks was utilized and long pending work of Deep Screening in
suburban section i.e SC-FM and SC-BMO sections was taken up and completed.
Rebuilding of Br No: 74 on SC-DHNE section –
The work of Rebuilding of Br No: 74 in UR yard on SC-DHNE section has been taken duly
taking a mega block of 74 Hrs i.e from 08.00 Hrs of 16.05.20 to 00.00 Hrs of 19.05.20. (Work
is being executed by RVNL as a part of Doubling work of SC-MBNR section)
(Note: This work has resulted in saving of Rs 10 Crores to Railways, since being
executed by RVNL as a part of SC- MBNR doubling work.)
Rebuilding of existing stone top culvert Bridge No: 197 with RCC boxes between
GLY-JCL stations on SC-DHNE section has been taken up and completed in the
shadow of mega block at Br No: 74 on 17.05.20. (Work at Br No: 74 was being
executed by RVNL as a part doubling work of SC-MBNR section)
Rebuilding of Br No: 109 & 196 have also completed as a part of Doubling of SC-
MBNR section by RVNL.
22