iii.  BCM 290 machine, which is working in the Division is about 30 Yrs old machine. The
                   progress achieved by the machine is about 64 Km in 09 Months, which is the highest
                   ever progress in the History of working of BCM-290 machine.

               iv.  During  lockdown  period,  when  passenger  carrying  train  traffic  was  less,  the
                   opportunity of traffic blocks was utilized and long pending work of Deep Screening in
                   suburban section i.e SC-FM and SC-BMO sections was taken up and completed.


                 Rebuilding of Br No: 74 on SC-DHNE section –

            The work of Rebuilding of Br No: 74 in UR yard on SC-DHNE section has been taken duly
            taking a mega block of 74 Hrs i.e from 08.00 Hrs of 16.05.20 to 00.00 Hrs of 19.05.20. (Work
            is being executed by RVNL as a part of Doubling work of SC-MBNR section)























            (Note: This work has resulted in saving of Rs 10 Crores to  Railways, since being
                       executed by RVNL as a part of SC- MBNR doubling work.)

                 Rebuilding of existing stone top culvert Bridge No: 197 with RCC boxes between
                   GLY-JCL  stations  on  SC-DHNE  section  has  been  taken  up  and  completed  in  the
                   shadow  of  mega  block  at  Br  No:  74  on  17.05.20.  (Work  at  Br  No:  74  was  being
                   executed by RVNL as a part doubling work of SC-MBNR section)






















                 Rebuilding of Br No: 109 & 196 have also completed as a part of Doubling of SC-
                   MBNR section by RVNL.