Foundation Depth Determination                                                                                                    Consideration in Shallow Foundation Design




                                                                                                                                                      i.   Pad footing should not be constructed on fill ground.
                      •  Must be deep enough to exclude undermining by flowing water


                      •  Must be deep enough for stability

                      •  Must be deep enough to avoid swelling and shrinkage effects due to water                                                                         Fill

                       • Depth of shallow foundation practiced by JKR is 1.5m ≤ D ≤ 3.0m
                                                                                                                                                      iii.  Shallow foundation shall not be constructed on partially cut and fill ground






                                                                                                                                                                                                                      Notes:
                                                                                                                                                                             Fill                  Cut                OGL : Original Ground Level
                                                                                                                                                                                                                      PL    : Platform Level



                                                                                                                                                      iv.  Shallow foundation is not advisable to be constructed near slope without stability
                                                                                                                                                           analysis study done











                                                                                                                                                                                              Safe Distance