Minimum Requirement for Pile Load Test   Acceptance Settlement Criteria





 •   Maintain Load Test (MLT):   •   For pile load test, based on JKR Standard Specification For Building Works 2014,
 –  1% of the total pile points or 2 nos per pile size /pile type, whichever is higher   Clause 2.9.6.3:



 •   Pile Dynamic Analyzer (PDA):     The total settlement (δ ) under Working Load (WL) ≤ 12.5mm; or
                                                        WL
 –  3% of the total pile points for normal ground condition; and
 –  7% for erratic ground condition     The total settlement (δ 2xWL ) under twice the working load (2*WL) ≤ 38.0mm or

                                10% of pile diameter / width whichever is the lower value; or

    Pile Type   Duration After Driven     The residual settlement (δ residual ) after removal of the test load at working load ≤

                                [(dia. of pile or diagonal width for non-circular pile /120) + 4]mm or 12.5mm

    End Bearing Pile   7 days      whichever is the lower value.

 Combination of end bearing & skin friction
 pile       14 days


    Friction pile, borepile and micropile   28 days

    Table 16: Minimum Waiting Period to Carry Out Load Test

             Note : Recommended duration of pile test execution based on JKR practice.







 68  PUBLIC WORKS DEPARTMENT MALAYSIA                                                          GEOTECHNICAL ENGINEERING HANDBOOK  69