Page 176 - BASIC GUIDELINE FOR QS
P. 176
Professional Practice: Guideline for Quantity Surveyor Chapter 5
5.10 Differences Between Tender Document Based on Bill Of Quantities and
Tender Document Based on Drawings and Specification
No Based On Bill Of Quantities Based On Drawing and Specification
1. Tender Notice Tender Notice
Checklist to submit tender Checklist to submit tender
Form of tender Form of tender
Instruction to tenderer Instruction to tenderer
Conditions of tendering Conditions of tendering
Letter of acceptance Letter of acceptance
Standard Form of Contract Standard Form of Contract :
: (JKR203)
(JKR203A) PAM 2006 without Quantities
PAM 2006 with Quantities Addendum of Conditions of
Addendum of Conditions of Contract
Contract Specification
Specification Preliminaries
Preliminaries Preambles to all trade
Preambles to all trade Schedule of rate
Bill of quantities Final Summary of Tender
Final Summary of Tender Appendices
Appendices Drawings
Drawings
2. Long time to prepare because Short time to prepare because no need a
need a detail project. detail project.
3. Suitable to construct a difficult Suitable to construct a standard project.
project.
4. Measurable quantities to be part All items of work specified in the form of
of the contract of right size works drawings and specifications.
to be executed.
5. In this way a contractor can be No BQ are given.
165