Page 176 - BASIC GUIDELINE FOR QS
P. 176

Professional Practice: Guideline for Quantity Surveyor                                                     Chapter 5



                   5.10   Differences  Between  Tender  Document  Based  on  Bill  Of  Quantities  and

                          Tender Document Based on Drawings and Specification

                     No       Based On Bill Of Quantities        Based On Drawing and Specification

                     1.          Tender Notice                      Tender Notice

                                 Checklist to submit tender         Checklist to submit tender
                                 Form of tender                     Form of tender
                                 Instruction to tenderer            Instruction to tenderer

                                 Conditions of tendering            Conditions of tendering
                                 Letter of acceptance               Letter of acceptance

                                 Standard Form of Contract          Standard Form of Contract :
                                  :                                   (JKR203)

                                  (JKR203A)                           PAM 2006 without Quantities
                                  PAM 2006 with Quantities           Addendum of Conditions of

                                 Addendum of Conditions of           Contract
                                  Contract                           Specification
                                 Specification                      Preliminaries

                                 Preliminaries                      Preambles to all trade
                                 Preambles to all trade             Schedule of rate

                                 Bill of quantities                 Final Summary of Tender
                                 Final Summary of Tender            Appendices

                                 Appendices                         Drawings
                                 Drawings


                     2.    Long  time  to  prepare  because  Short time to prepare because no need a

                           need a detail project.              detail project.

                     3.    Suitable  to  construct  a  difficult  Suitable to construct a standard project.
                           project.

                     4.    Measurable  quantities  to  be  part  All  items  of  work  specified  in  the  form  of
                           of the contract of right size works  drawings and specifications.
                           to be executed.

                     5.    In  this  way  a  contractor  can  be  No BQ are given.