Professional Practice: Guideline for Quantity Surveyor                         Chapter 2



                   D)     Design Development

                          While the Concept stage was only a general approach on a design, the design
                          development  will  be  more  detail  on  it.  The  design  team  will  identify  the  detail
                          information from various sources to full fill the client needs and the regulation by

                          the local authority. It is a process of completing the project brief and prepares the
                          certain proposal including item below:

                                Design approach
                                Method of Construction

                                Specification
                                Building amenity

                                Building structure
                                Cost


                          The  information  from  the  project  brief  is  still  needed  at  this  stage.  Sufficient
                          information is important because it can avoid uncertainty and to ease the design
                          team completing the design and select the quality of material which are suitable

                          and follow the client needs and client requirements.
                                 After  this  stage  the  project  brief  is  no  longer  can  be  amend.  Several

                          choices of design and construction method to be consider and QS will prepare
                          the  estimate  cost  that  shall  include  initial  cost  and  future  cost  such  as
                          maintenance cost.

                                 The  engineer  will  prepare  the  structural  design.  The  architect  design
                          (drawing) and engineer design (drawing) are different to each other and both play
                          a  major  role  in  construction.  Engineer  will  prepare  the  engineering  structural

                          drawing base on calculated load to ensure the building can be built without any
                          problem.
                                 For  servicers  engineer  (mechanical  and  electrical),  the  job  scope  are

                          different. Services engineer is responsible to design all the building services and
                          facilities such lift, escalator, cold and hot water system, fire system, electrical, air

                          conditioning,  garbage  disposal  system,  and  etc.  Client  agreement  is  important
                          before the architect can apply and getting approval from the local authority.
                          In this stage, the quantity survey job become more detail and its cover all area of

                          costing (Cost Planning). The information given by the architect and engineer are