2/27/24, 10:28 AM Dubai Municipality initiates project to develop Dubai Creek pier, upgrade support walls
The project is set to be implemented in two phases, with the initial phase involving
the restoration of a 2.1 km stretch along the Deira side of Dubai Creek. The site will
be divided into multiple sections, and each segment will be sequentially patterned to
ensure uninterrupted docking traffic. The second phase will cover a 2.3 km length
on the Bur Dubai side.
Global Reputation
Dawoud Al Hajri, Director-General of Dubai Municipality, stated that the project
highlights Dubai Municipality's commitment to transforming Dubai into a more
attractive and innovative city by enhancing various elements and services it offers
through the strategic and sustainable development of all coastal facilities and
infrastructure in the Emirate. The goal is to solidify Dubai's position as a global
tourism hub and augment its economic and commercial prosperity.
Al Hajri said, "The project is set to improve security and safety measures for
maritime traffic and commercial operations within Dubai Creek. As a significant
symbol of the city's growth, Dubai Creek serves as a vibrant artery at the heart of
Dubai.
Facilitating the passage of over 13,000 ships annually, it plays a key role in fostering
the economic and social prosperity of the emirate. Additionally, the creek further
supports commercial dealings with neighbouring markets in the region."
"We have implemented several measures to mitigate the risks posed by climate
change and rising sea levels, closely monitoring changes on both sides of the
creek. Furthermore, we have conducted technical studies to devise construction
designs that can enhance the efficiency of the marine docks on both banks.
These designs adhere to the highest global standards, ensuring the preservation of
the supporting walls' stability and safeguarding against increased flooding during
seasonal weather conditions." Al Hajri added.
Comprehensive work
The project's 14-month timeline includes the restoration of the 2.1 km Deira pier,
which involves replacement and the rehabilitation of damaged sections of the
concrete wall, reaching a depth of 8 meters and increasing its height to 3 meters.
These improvements aim to ensure the safe docking of ships in the area.