16 Up gradation of carriage watering facilities on PF No. 8 & PF. PA 24396
No. 9&10 ( 2 lines) & dedicated over head water tank at SC
17 PA Total 159895 21985 101379
18 Provision of Automatic Coach Washing Plant at SC WS 18000
19 Provision of input water and Electrical supply up to the WS 4984
Automatic coach washing plant (ACWP) at SC
WS Total 0 0 22984
20 Secundarabad-Capacity argumentation of running room at OSW 13190
Secunderabad .
OSW Total 0 0 13190
B Works in Progress (Rs. In '000s)
Year of Name of work PH Cost TDC Remarks
sanc
16-17 Construction of new crew lobby and box room for TF 14370 Dec'21 Construction of building completed.
augmentation of Running room capacity as per RB norms and Finishing works are going on. Final variation
provision of lift at SC running room under process.Lift work to be taken up.
TF Total 14370
08-09 Secunderabad Coaching Depot - Extension of IOH Shed. WS 28017 Nov'21 BG of Rs.85 lakhs provided for 2021-22.
Civil - Extension of IOH shed completed,
Path ways and drainage works are under
progress.
18-19 SC Coaching Depot- Upgradation of 4 pit lines from non WS 123139 Mar'23 Mech: 2 nos of EOT cranes received on
standard design to standard CAMTECH design pit lines. 04.09.21 and commissioned on 15.09.2021.
COFMOW debits for ` 95.32 lakhs was
forced by Ex-parte
Civil: Tender not floated due to paucity of
funds. BG of Rs.1000 provided for 2021-22.
WS Total 151156