15-16 Secunderabad - Repl. of central foot over bridge PA 201876 Dec'21 For new central FOB Gangway launching
was completed from PF 1 to 6/7 ,flooring is
Completed. De-launching of central FOB
was completed in a block of 10 hours.
.Foundation works are completed in all PF's
and Columns are erected in in all Platforms
including staircase. Further , work is in good
progress.
17-18 Secunderabad- Proposed Extension of foot over bridge PA 21931 Dec'21 Foundation on platform no 6/7,8/9 and PF
connecting PF No.6 & 7 to 10 between KZJ end FOB and no.10 ,columns fabrication was completed,
Central FOB . Columns on PF No.6,7,8,9,10 was
erected.Launching of gangway was
completed on PF 9-10. Further work of
gang way fabrication ,stair case are in
progress."
18-19 Replacement of existing aged Non - RDSO Type Coach PA 29651 Nov'21 CIB's commissioned on all 10 platforms .
Guidance Boards , Train information Boards display boards at Multi line boards near main councorse /
SECUNDERABAD station waiting hall is in advanced stage of
completion.
18-19 Secundarabad- Ancillary work to the extension of FOB from PA 21548 Dec'21 Works of S&T ,
PF.no.6/7 to PF No.10 for construction of additional stair ways Electrical(General),Electrical(TRD) are in
and connecting works etc. progress at SC station to facilitate for FOB
extension. Work was sanctioned as per
dy/CE/P&D lr.No.W.563/1/91/PWP/2018-
19/Umb. sanction/ Vol.II.dt.04-07-18.
Telecom work in progress.