18-19 Secundarabad~~Provision of GLR 25 Lakhs litres capacity with PA 24863 Mar'21 Work awarded.Land has to be acquired
pipe line network including provision of 10 Lakhs capacity OH from HYB division.Location has to be
RCC tank at SC finalised.
19-20 Secundarabad~~Remodeling of Parcel Office at PA 14900 Dec'21 Shed work and flooring works are
Secunderabad station completed.Miscellaneous work is in
progress.
19-20 Provision of CIBs at SC Stations & Two 5 liner TIBs and four at a PA 5000 Dec'21 Physical installation is completed.
glance Coach Guidance Boards for new FOB at SC Commission is in progress.
21-22 Provision of X-ray Baggage Inspection System for the use of RPF PA 1542 Mar'22 Estimate sanctioned. Indent under process.
posts at SC railway station.
PA Total 321311
18-19 SC Division:- Proposed Service Building for staff at lower yard OSW 4963 Dec'21 Slabs casted and plastering work is in
progress.
OSW Total 4963
Summary (Fig in 000'S)
PH Completed In Progress Total
TF 0 14370 14370
WS 22984 151156 174140
OSW 13190 4963 18153
PA 291959 321311 321311
Total 36174 491800 527974