18-19   Secundarabad~~Provision of GLR 25 Lakhs litres capacity with          PA         24863        Mar'21     Work awarded.Land has to be acquired
               pipe line network including provision of 10 Lakhs capacity OH                                            from HYB division.Location has to be
               RCC tank at SC                                                                                           finalised.

       19-20   Secundarabad~~Remodeling of Parcel Office at                          PA         14900        Dec'21     Shed work and flooring works are
               Secunderabad station                                                                                     completed.Miscellaneous work is in
                                                                                                                        progress.

       19-20   Provision of CIBs at SC Stations & Two 5 liner TIBs and four at a     PA          5000        Dec'21     Physical installation is completed.
               glance Coach Guidance Boards for new FOB at SC                                                           Commission is in progress.
       21-22   Provision of X-ray Baggage Inspection System for the use of RPF        PA         1542        Mar'22     Estimate sanctioned. Indent under process.
               posts at SC railway station.
               PA Total                                                                        321311

       18-19   SC Division:- Proposed Service Building for staff at lower yard      OSW          4963        Dec'21     Slabs casted and plastering work is in
                                                                                                                        progress.
               OSW Total                                                                    4963

                                                                                  Summary (Fig in 000'S)
                                                                                      PH     Completed     In Progress                      Total

                                                                                      TF          0           14370                         14370
                                                                                     WS         22984        151156                        174140

                                                                                    OSW         13190         4963                          18153
                                                                                     PA        291959        321311                        321311

                                                                                    Total       36174        491800                        527974