Page 207 - Project+
P. 207

PV = 75,000


         AC = 71,000

         EV = 70,000

     Now let’s calculate the CV using these numbers:

         70,000 – 71,000 = –1,000

     The result is a negative number, which means that costs were higher than what was
     planned for the work that was completed as of December 1. These costs are usually not
     recoverable. If the result was a positive number, it would mean you spent less than
     what you planned for the work that was completed as of December 1.


     Schedule Variance


     Schedule variance, another popular EVM variance, compares an activity’s actual
     progress to date to the estimated progress and is represented in terms of cost. It tells
     you whether the schedule is ahead of or behind what was planned for this period. This
     formula is most helpful when you’ve used the critical path methodology to build the
     project schedule. The schedule variance (SV) is calculated as follows:

         SV = EV – PV

     Plug in the numbers:


         70,000 – 75,000 = –5,000

     The resulting schedule variance is negative, which means you are behind schedule or
     behind where you planned to be as of December 1.

     Together, the CV and SV are known as efficiency indicators for the project and can be
     used to compare the performance of all the projects in a portfolio.


     Performance Indexes

     Cost and schedule performance indexes are primarily used to calculate performance
     efficiencies, and they’re often used to help predict future project performance.

     The cost performance index (CPI) measures the value of the work completed at the
     measurement date against the actual cost. It is one of the most important EVM

     measurements because it tells you the cost efficiency for the work completed to date or
     at the completion of the project. If CPI is greater than 1, you are spending less than
     anticipated at the measurement date. If CPI is less than 1, you are spending more than
     anticipated for the work completed at the measurement date.

     The cost performance index (CPI) is calculated this way:

         CPI = EV / AC

     Plug in the numbers to see where you stand:





                                                            207
   202   203   204   205   206   207   208   209   210   211   212