    19.  Project costs when displayed graphically over time represent which of the
         following?

         A.  S curve

         B.  C curve

         C.  Evenly distributed expenditures

         D.  Erratic expenditures

   20.  You are determining the risk score for each of the risks in your risk register. You

         need which of the following to determine this score? Choose two.

         A.  Response plans

         B.  Risk owners

         C.  Probability the risk will occur

         D.  Contingency reserves

         E.  Risk trigger scores

         F.  Impact if the risk occurs