Trigger Stakeholder                    Reason                                Method            Timing of

                                                                                                    Notification

     Project       All                      Obtain sign-off.                      Sign-off          At completion
     planning                                                                     meeting           of planning
     complete                                                                                       phase

     Project       Sponsor and              Obtain approval/deferral of Project                     Regularly
     change        affected                 change.                               change            scheduled
                   stakeholders                                                   management change
                                                                                  meeting           meeting

     Risk          Stakeholder A,           Update of risk events                 Special risk      Immediate
     register      Stakeholder B,           occurring, response plans             meeting,          and at
     updates Stakeholder C,                 put into action, or                   project           regularly
                   Stakeholder D            notification of new risks             meeting           scheduled
                                                                                                    project

                                                                                                    meeting

     Resource Sponsor,                      Inform stakeholders of                Special           Immediate
     changes impacted                       impacts, delays, or risks             meetings,         and at
                   stakeholders             from resource changes.                project           regularly
                                                                                  meetings          scheduled
                                                                                                    project
                                                                                                    meeting








       Main Street Office Move: The Communication Plan
       The project plan for the move is coming together. You’re working on the

       communication plan and will obtain stakeholder approval once you meet with
       Kate. Here is what you know so far.

       The following table shows a partial communication plan for the Main Street Office
       Move project:


        Stakeholder            Communication Format of                             Method Responsible Frequency
        Name                   Type                      Communication                           Party



        Kate                   Project status            Written and verbal In                   Project             Weekly
        Sponsor                reports, budget,                                    person,       manager
                               schedule, moving                                    project

                               company updates,                                    meetings,
                               issues, risk events,                                printed
                               final project                                       report,
                               approval                                            email,