Risk and control of Information Systems





                           Changeover methods






               5.1   Changeover methods

                    Direct               Old system switched off and new system switched on

                                          Cheap but risky


                    Parallel             Old and new systems run together for some time, until it is
                                          felt safe to switch off the old.

                                          Costly (duplication) but less risky


                    Pilot                One part of the business changes over first and then plans
                                          rolled out to the rest of the business


                                          Should reduce some risks as can learn from the pilot but
                                          other locations may have different issues / problems


                    Phased               Introduce  new system one part of the business at a  time

                                          Less risky but takes longer