Subject E2: Project and Relationship Management




               14.2 A company is undertaking a project and has completed a risk assessment.

                     Match the following risk assessment scenarios to the most suitable risk
                     management strategy.



                    Risks with a low likelihood and a low                    TRANSFER
                    impact.




                    Risks with a high likelihood and a high                  ACCEPT
                    impact.




                    Risks with a low likelihood and a high                   REDUCE
                    impact.




                    Risks with a high likelihood and a low                   AVOID
                    impact.



               14.3 Which TWO of the following statements regarding the activities carried
                     out during the various stages of the project lifecycle are correct?

                     A     The main output of the initiating stage is the project quality plan (PQP).

                     B     One of the main techniques used at the planning stage of a project is the
                           Gantt chart which is used to determine the resource requirement for the
                           project.

                     C     During the executing stage, configuration management will be used to that
                           all changes within the project are properly managed and documentation is
                           controlled.


                     D     Reports are used within the controlling stage of the project. Exception
                           reports are used to highlight only the deviations from the plan.


                     E     The project team is disbanded at the post-completion stage of the project.