Subject E2: Project and Relationship Management
14.2 A company is undertaking a project and has completed a risk assessment.
Match the following risk assessment scenarios to the most suitable risk
management strategy.
Risks with a low likelihood and a low TRANSFER
impact.
Risks with a high likelihood and a high ACCEPT
impact.
Risks with a low likelihood and a high REDUCE
impact.
Risks with a high likelihood and a low AVOID
impact.
14.3 Which TWO of the following statements regarding the activities carried
out during the various stages of the project lifecycle are correct?
A The main output of the initiating stage is the project quality plan (PQP).
B One of the main techniques used at the planning stage of a project is the
Gantt chart which is used to determine the resource requirement for the
project.
C During the executing stage, configuration management will be used to that
all changes within the project are properly managed and documentation is
controlled.
D Reports are used within the controlling stage of the project. Exception
reports are used to highlight only the deviations from the plan.
E The project team is disbanded at the post-completion stage of the project.