Page 274 - E2 Integrated Workbook STUDENT 2018
P. 274
Subject E2: Project and Relationship Management
15.3 Which three of the following statements concerning project planning tools
and techniques are correct?
A A graphical aid for determining the total requirement for a specific
resource during the project is known as a product breakdown structure.
B A milestone is an event within a project that is clearly identifiable as a
measure of how far the project has progressed, and how far it has to run.
C The major document used within projects to detail the standards that must
be adhered to in order to ensure a successful development process is
known as the Project Initiation Document.
D The cost breakdown structure is used to generate the project’s financial
plan, or budget.
E Project management software can be used throughout the project for
planning, estimating, monitoring and reporting.
15.4 The Project Management Body of Knowledge (PMBOK) describes nine key
areas within projects.
Which of the following are these key areas? Select all that apply.
A Scope
B Communication
C Planning
D Finance
E Human resources
F Integration
268