Subject E2: Project and Relationship Management




               14.2 The correct matching is shown below:


                    Risks with a low likelihood and a low                    TRANSFER
                    impact.




                    Risks with a high likelihood and a high                  ACCEPT
                    impact.



                    Risks with a low likelihood and a high                   REDUCE
                    impact.




                    Risks with a high likelihood and a low                   AVOID
                    impact.



               14.3 The correct statements are C and D

                     The main output of the initiating stage is the project initiation document (PID).


                     The Gantt chart is one of the main techniques used at the planning stage of a
                     project, but it used to determine the timing for the project. The resource
                     histogram is the main technique used to determine the resources.

                     The project team is disbanded at the closing stage of the project. The post-
                     completion stage is held a few months after the end of the project.