Subject E2: Project and Relationship Management
14.2 The correct matching is shown below:
Risks with a low likelihood and a low TRANSFER
impact.
Risks with a high likelihood and a high ACCEPT
impact.
Risks with a low likelihood and a high REDUCE
impact.
Risks with a high likelihood and a low AVOID
impact.
14.3 The correct statements are C and D
The main output of the initiating stage is the project initiation document (PID).
The Gantt chart is one of the main techniques used at the planning stage of a
project, but it used to determine the timing for the project. The resource
histogram is the main technique used to determine the resources.
The project team is disbanded at the closing stage of the project. The post-
completion stage is held a few months after the end of the project.