Risk and the risk management process




               4.2 Risk mapping

               A common qualitative way of assessing the significance of risk is to produce a ‘risk
               map’:


               Risks can be plotted on a diagram, as shown.

                                                             Impact/consequence
                                                       Low                             High



                                               Further analysis

                                 High              required?                    Highest priority


                Probability

                /likelihood

                                             Risks can probably                 Further analysis

                                 Low             be accepted                        required?




               The risk management strategies that will be adopted depend on how risk is assessed
               on this map.

                    Transfer

                    Accept


                    Reduce

                    Avoid



                  Illustrations and further practice



                  Now review illustration and try TYU question 5