Chapter 10
Step (2) Determine the stage of completion of the contract
Two methods exist to determine stage of completion:
cost basis
work certified basis.
The exam question will inform you of which method is relevant for
your scenario.
Stage of
completion
Work certified
Cost basis basis
Costs incurred to date Work certified to date
––––––––––––––––––––– × 100 –––––––––––––––––––––– × 100
Total costs for the contract Total revenue for the contract