Construction contracts





                  Example 10.1



                  Mane builds oil rigs for companies operating in the oil industry. Mane applies
                  IAS 11 Construction contracts.

                  The entity has three contracts in process at the year-end 30 April 20X1:

                                                                A             B             C
                                                              $000          $000          $000

                  Contract price                               450           378           900
                  Work certified to date                       338           252           180

                  Costs incurred to date                       346           421           198
                  Estimated costs to complete                   43           151        unknown
                  Progress billings                            324           202           144


                  Required:

                  Prepare extracts from the financial statements for each of the three
                  projects, assuming that revenues and profits are recognised on the work
                  certified basis.