Construction contracts




               Step (3) Calculate the figures for the current period statement of profit or loss

               Profitable contracts


                                            [Completion % (step 2) × contract price] – previously
                 Revenue               x
                                            recognised revenue.
                                            [Completion % (step 2) × total costs] – previously
                  Cost of sales       (x)   recognised costs.
                                     ––––
                  Gross profit         x
                                     ––––



               Loss making contracts


                                           [Completion % (step 2) × contract price] – previously
                 Revenue             x
                                           recognised revenue.
                 Cost of sales       (x)   β

                                   ––––
                  Gross profit       X     Total loss from step (1) recognised immediately.
                                   ––––