Chapter 18










                   Example 6




                   For every machine hour a unit uses in production cost centre 1 it will pick up
                   $5.44 and for every labour hour a unit uses in production cost centre 2, it will
                   pick up $10.30.

                   Consider the following data for product XX:

                                              Prod cost centre 1  Prod cost centre 2

                   Labour hours per unit               5                       3
                   Machine hours per unit              2                      4

                   The overhead one unit of product XX will pick up is:

                   Production cost centre 1: 2 machine hours × $5.44 = $10.88

                   Production cost centre 2: 3 labour hours × $10.30 = $30.90

                   Remember: this is the overhead, or indirect cost, to be picked up by
                   each unit of XX. To find the total cost of a unit of XX the direct costs
                   must be added on.