Page 194 - F2 Integrated Workbook STUDENT 2019
P. 194

Chapter 7




               Step (2) Determine the contracts’ progress towards completion

               Two methods exist to determine progress towards completion:

                                The exam question will inform you of which method is relevant for
                                your scenario.



                                                       Progress
                                                       towards

                                                     completion





                                   Input method                          Output method
                                 (costs incurred)                      (Work performed)





                    Costs incurred to date                            Work/time to date

                  ––––––––––––––––––––– ×   100                  ––––––––––––––––––––––          × 100
                  Total costs for the contract                  Total revenue/timeframe for
                                                                         the contract