Revenue from contracts with customers





                  Example 7.8



                  Mane builds oil rigs for companies operating in the oil industry. The rigs are
                  specialised and have no alternative use.

                  The entity has three contracts in process at the year-end 30 April 20X1:

                                                                A             B             C
                                                              $000          $000          $000

                  Contract price                                450           378           900
                  Work certified to date                        338           252           180

                  Costs incurred to date                        346           421           198
                  Estimated costs to complete                    43           151      unknown
                  Progress billings                             324           202           144


                  Required:

                  Prepare extracts from the financial statements for each of the three
                  projects, assuming that revenues and profits are recognised on the output
                  basis.