Page 398 - PM Integrated Workbook 2018-19
P. 398

Chapter 15





                   (c)  Office cleaning expenses of £125 for next month. The office is cleaned
                        by contractors and the contract can be cancelled by giving one month’s
                        notice.


                        Is this cost relevant to a decision to close the office?

                        This is not a relevant cost for next month since it will be incurred even if
                        the contract is cancelled today. If a decision is being made to close the
                        office, this cost cannot be included as a saving to be made next month.
                        However, it will be saved in the months after that so it will become a
                        relevant cost saving from month 2 onwards.

                   (d)  Expenses of £75 paid to the marketing manager. This was to reimburse
                        the manager for the cost of travelling to meet a client with whom the
                        company is currently negotiating a major contract.


                        Is this cost relevant to the decision to continue negotiations?

                        This is not a relevant cost of the decision to continue with the contract.
                        The £75 is sunk and cannot be recovered even if the company does not
                        proceed with the negotiations.