Chapter 12










                  Example 3



                   ABC has determined that their production budget for product X next year will
                   be 10,500 units. Every unit of product X is expected to use 1.5 hours of labour
                   time and the expected labour cost per hour is $10.

                   Calculate the budgeted labour cost.

                   Solution

                   Labour hours = production budget × standard labour time per unit


                   Labour hours = 10,500 units × 1.5 hours = 15,750 hours

                   Labour cost = labour hours × cost per hour

                   Labour cost = 15,750 hours × $10/hour = $157,750