Answers










                   Example 2



                   An audit firm plans a job with the following staff requirement:

                   Staff members        Time allowed           Cost per hour               Total


                   Audit manager           5 hours                  $30                    $150
                   Supervisor             20 hours                  $15                    $300

                   Junior trainee         35 hours                  $10                    $350

                   Total                  60 hours                                         $800


                   The actual hours worked on the job were:

                   Audit manager           6 hours

                   Supervisor             15 hours
                   Junior trainee         45 hours


                   Total                  66 hours

                   Calculate the labour mix and yield variances using both the individual
                   and weighted average methods.


                   Solution

                   Labour yield variance

                   This will be the same under both methods.

                   The standard yield = 66 hours should yield 1.1 jobs