Page 48 - P1 Integrated Workbook STUDENT 2018
P. 48
Chapter 3
Solution
Standard Ultra
Selling price per unit $80 $120
Material costs per unit $20 $24
Throughput $60 $96
Throughput per hour at bottleneck $60 $48
Production rank 1 2
Production plan:
Units Hours per Bottleneck Throughput
unit hours used $
Standard 40,000 1 40,000 2,400,000
Ultra 5,000 2 10,000 240,000
–––––––––
2,640,000
Factory costs 2,000,000
–––––––––
Gross profit 640,000
–––––––––
Illustrations and further practice
Now try examples 2 and 3 from Chapter 3.
44