Answers









                   Example 3





                   The first unit of a new product is expected to take 100 hours. An 80% learning
                   curve  is known to apply.

                   Calculate:

                   (a)  The average time per unit for the first 16 units

                         a = 100                    b = –.03219                  x = 16


                                                    Y = 100 × 16  –.0329

                                                    Y = 40.96 hours

                   (b)  The average time per unit for the first 25 units

                         x = 25


                         Y = 100 × 25  –.0329

                         Y = 35.48 hours

                   (c)  The time it takes to make the 20th unit


                         x = 20                     Y = 100 × 20  –.0329         Y = 38.12 hours
                         Total time for 20 units = 38.12 × 20 = 762.42 hours


                         x = 19                     Y = 100 × 19  –.0329         Y = 38.76 hours

                         Total time for 19 units = 38.76 × 19. = 736.50 hours

                         So, to make the 20th unit, 762.42 – 736.35 = 26.07 hours