Page 30 - FINAL CFA SLIDES JUNE 2019 DAY 2
P. 30

LOS 7.b: Contrast the NPV rule to the IRR rule, and                          Session Unit 2: Discounted Cash Flow Applications
      identify problems associated with the IRR rule..


        NPV + = Accept project, it will increase shareholder wealth.

        NPV - = Reject project, it will decrease shareholder wealth.

        •    When two projects are mutually exclusive (only one can be accepted), the project with the higher positive NPV should
             be accepted.

        IRR decision rule:

        IRR > firm’s (investor’s) required rate of return = Accept!  IRR < firm’s (investor’s) required rate of return = Reject!


        Problems Associated With the IRR Method

        Example: Conflicting decisions between NPV and IRR: Assume NPV and IRR analysis of two mutually exclusive
        projects produced the results shown in the following figure. As indicated, the IRR criteria recommends that Project A should
        be accepted. On the other hand, the NPV criteria indicates acceptance of Project B. Which project should be selected?


                                                                                        Answer: Investing in Project A increases
                                                                                        shareholder wealth by $2,272.72, while
                                                                                        investing in Project B increases shareholder
                                                                                        wealth by $6,363.64. Since the overall goal of
                                                                                        the firm is to maximize shareholder wealth,
                                                                                        Project B should be selected because it adds
                                                                                        the most value to the firm.



        The NPV method assumes the reinvestment of a project’s cash flows at the opportunity cost of capital, while the IRR method assumes that the
        reinvestment rate is the IRR. Always select the project with the greatest NPV when the IRR and NPV rules provide conflicting decisions.
   25   26   27   28   29   30   31   32   33   34   35