Investment appraisal techniques





                           Project abandonment





                             During a post-completion appraisal, it may be realised that the project is
                             not likely to be so profitable as first thought, and the possibility of
                             abandoning it or terminating it early should be considered.


                             Abandoning the project is only necessary when the net discounted
                             expected future cash flow of the project becomes negative.


                             To value an option, compare the expected NPV without abandonment
                             with the expected NPV with abandonment.