Page 211 - Microsoft Word - 00 CIMA F1 Prelims STUDENT 2018.docx
P. 211

Answers to supplementary objective test questions




               CHAPTER 2 – THE MODERN BUSINESS ENVIRONMENT


               2.1  D


               2.2  Prevention: The cost of implementing a system to prevent defects before they
                     can actually occur.

                     Appraisal: The costs of inspection and testing.

                     Internal Failure Costs: Costs from a failure. However, this failure is found before
                     the product is presented to the customer.

                     External Failure Costs: Costs from a failure. However, this failure is found by
                     the customer.


               2.3   D

                     BPR should not be seen as a mere cost cutting exercise although long term
                     savings may well result through improved processes. The important point is that
                     it is not a one-off, so III is wrong. BPR is a radical rethink, so it is much more
                     than small incremental changes – this sounds more like Kaizen.

                     BPR is often driven by environmental changes and does require a strategic
                     outlook, so IV is correct. It is also often the case that complex organisations are
                     made much simpler by 'delayering' or removing unnecessary activities.


               2.4   Options (iii) and (iv) are correct.

                     The throughput = Selling price – material costs. Since selling price is $30 and
                     the throughput is $12, material costs are $18.  Since the product also requires
                     labour and variable overheads, the total variable cost must be higher than
                     $18 so option 1 is wrong.

                     The return per factory hour is throughput per unit/product time in bottleneck
                     resource which is 12/(5,600/700) = 12/8 = $1.5 so option 2 is wrong.

                     The cost per factory hour is total factory cost/total time on bottleneck =
                     $3,920/5,600 = $0.7 so option 3 is correct.

                     The throughput accounting ratio is return per factory hour/cost per factory hour
                     =$1.5/$0.7 which is greater than 1 so option 4 is correct.

                     Management should be aiming to maximise the throughput accounting ratio so
                     option 5 is wrong.







                                                                                                      205
   206   207   208   209   210   211   212   213   214   215   216