Page 14 - ATC DT IAproposal 061621_Neat
P. 14

05
                                               SCHEMMER PROJECT EXPERIENCE












































            R & R COMMERCE PARK WAREHOUSES, PHASES I-III | OMAHA, NE                                                                  WARREN DISTRIBUTION ADDITION | COUNCIL BLUFFS, IA

            Schemmer was retained by R&R Realty Group to provide design services for a warehouse prototype design for the first       Schemmer was retained by Warren Distribution to provide design services for a 211,000 SF addition to its Council Bluffs
            of four, 250,000-300,000 SF core and shell warehouse buildings with a 32-foot clear interior height and 50-foot column    warehouse and distribution center. The project expanded their current 165,000 SF distribution center located on a 15-acre
            bay spacing. It included space for warehousing or manufacturing. Schemmer provided architecture, structural and           site. Warren Distribution produces lubricants and industrial fluids and the company needed to expand their facility to handle
            construction administration services.                                                                                     increased domestic and international demand for its manufacturing products and packaging.
            Phase II for a second warehouse has just completed construction. Phase III has been designed, bid and is currently        Schemmer’s services include: Due Diligence (site planning and zoning review); Civil Engineering; Stormwater Management;
            awaiting permitting.                                                                                                      Stormwater Modeling; Survey; Geotechnical Engineering; Architecture; Structural, Mechanical and Electrical Engineering;
            ORIGINAL TOTAL PROJECT BUDGET                       TOTAL CHANGE ORDERS                                                   Stormwater Pollution Prevention Plan and NPDES Permitting; USACE 404 Permitting; USACE 408 Submittals; Construction
            $45,000,000                                         $115,000                                                              Materials Testing; and Construction Staking.
            FINAL TOTAL PROJECT COST                                                                                                  ORIGINAL TOTAL PROJECT BUDGET                      FINAL TOTAL PROJECT COST
            Phase I: $10,100,000; Phase II: $10,800,000; Phase III: $11,800,000;  Phase IV: TBD                                       $9,150,000                                         $9,500,000
            SCHEDULE INFORMATION                                                                                                      TOTAL CHANGE ORDERS                                SCHEDULE INFORMATION
            Phase I: Design - 2017; Construction - 2018; Design was completed on schedule. Construction completed two months later    $350,000 ($300,000 of which were scope additions by the   Design - 2018; Construction - 2018/19. Design was
            than originally scheduled due to weather and the precast manufacturer’s product delay and slow delivery.                  client)                                            completed on schedule.
            Phase II: Design - 2017; Construction - 2019/20; Design was completed on schedule.                                        APPROACH TO RESOLVING SCOPE/BUDGET CONFLICTS DURING DESIGN PROCESS
            Phase III: Design - 2020; Est. Construction - 2020/21; Design was completed on schedule.                                  We had multiple conversations regarding scope and budget during design. Most were centered around the impacts of
            APPROACH TO RESOLVING SCOPE/BUDGET CONFLICTS DURING DESIGN PROCESS                                                        high-piled storage requirements to the project and interfacing with the Client's insurance carrier.
            None required. This client had a very good idea what the buildings should cost based on the scope.                        HIGHLIGHTED PROJECT CHALLENGES/SOLUTIONS/SUCCESSES
            HIGHLIGHTED PROJECT CHALLENGES/SOLUTIONS/SUCCESSES                                                                        Fast track permitting and design were successes for the project along with overcoming site constraints and legacy Code
            The projects were successful in meeting project design schedule and budget while meeting the challenges of the City's     interpretations in order to construct a large enough building to meet the Client's Program.
            aesthetic requirements for industrial projects.                                                                           TEAM MEMBERS
            TEAM MEMBERS                                                                                                              Jason Heinze, PE, SE, LEED AP - Principal/Project Manager; Dan Kerns, AIA - Architect; Jeff Kulhanek, PE - Mechanical
            Jason Heinze, PE, SE, LEED AP - Principal/Project Manager; Dan Kerns, AIA - Project Manager/Architect; Kevin Wenninghoff,   Engineering; Joe Binge, PE - Electrical Engineering; Rob DuVall, PE - Civil/Site Engineering
            SE - Structural Engineering; Rob DuVall, PE - Civil/Site Engineering; Aaron Ferguson - Construction Administration        REFERENCE
            REFERENCE                                                                                                                 Donna Weeda, Warren Distribution, Inc - Chief Operating Officer | dweeda@wd-wpp.com | 402.977.5424
        14  Nate Franje, R&R Realty - Director of Project Development and Construction | franje.nate@rrrealty.com | 515.223.4500                                                                                                             15
   9   10   11   12   13   14   15   16   17   18   19