Page 13 - EOI_Wallace Bishop Retail Redevelopment
P. 13
RETAIL PORTFOLIO
BIG W MOUNT OMMANEY DAN MURPHY’S GLADSTONE DAN MURPHY’S WATERGARDENS
VALUE: $0.8 MILLION VALUE: $3.4 MILLION VALUE: $4.1 MILLION
Refurbishment of a Big W store as part of a roll Construction of a new 1200M² Dan Murphy’s Liq- Design and construct of new 1,442m² Dan Mur-
out aimed to improve the overall appearance of uor Store including Asphalt Carpark, Landscaping phy’s store. Scope of works include infrastructure
existing and new stores. Works include a general & Bioretention System. for future precinct buildings, car park and loading
upgrade of trading floors, new checkouts, upgrade bay.
of gondolas, floor vinyl upgrade and associated
building services.
WOOLWORTHS MARYBOROUGH BIG W GLADSTONE ALDI VERMONT SOUTH
VALUE: $11.0 MILLION VALUE: $2.7 MILLION VALUE: $1.8 MILLION
Reinstatement of an extensively flood damaged The building works includes construction of a new Minor demolition of internal walls, fitout of existing
supermarket. Scope of works includes guttering of mezzanine floor and alterations to existing store premises for use as an ALDI supermarket.
existing supermarket and new store rebuild includ- which included asbestos removal, floor removal
ing a new shopfront with architecturally aesthetic and replacement, all electrical refurbishment and
façade including glazing. All elevations have been alterations to the store, fire alterations which incor-
modernised with new painted CFC, render and porated tanks, new booster pumps and storage.
metal cladding to give a renewed look. A new pair
of travelators and air lock will also be installed.
WOOLWORTHS JINDALEE WOOLWORTHS BOX HILL ALDI BOX HILL SOUTH
VALUE: $1.0 MILLION VALUE: $1.4 MILLION VALUE: $6.0 MILLION
Construction of a new Woolworths store in an Refurbishment of an existing supermarket located Demolition of existing building and construction
existing building in accordance with 2011 design within a busy shopping centre. Due to restrictions of a new modern ALDI supermarket with an un-
kit. The works were completed in 12 weeks. on access and limitation on loads, helicopters derground carpark. One of the many architectural
were used to enable aerial lifts. features of the new store is the use of bevelled
edge precast panels.
13