INNOVATION AND VALUE ADDING


















           MAYFLOWER STAGE 2         We requested that the in-situ Rytek walls and in-situ concrete columns were
                                     redesigned as precast elements.  Although this design change was slightly
                                     more expensive than the originally specified methods there was an eight
                                     week time saving achieved in the completion of the concrete structure.
                                     Without this design change and associated reduction of the construction
                                     program, the project completion date would have been much later due
                                     to the extensive scope of additional works and variations throughout the
                                     project.
           EUNICE SEDDON HOME        The basement carpark retaining walls and lift shaft were redesigned at our
           WINTRINGHAM AND           cost from core-filled blockwork to precast to provide savings in construction
           WALLARA                   cost and project time.  Post tender negotiations identified the following cost
                                     savings that were accepted:

                                       ˃ Change rammed earth walls to rendered brickwork
                                       ˃ Redesign screw pile footing system and redesign roof frame to timber
                                      trusses
                                       ˃ Change shiplap WRC cladding to custom-orb Colorbond
                                       ˃ Change construction and insulation between bedrooms
                                       ˃ Change timber decking from radial sawn hardwood to treated pine
                                       ˃ Alternate light fitting suppliers and alternate lift manufacturer
           MONASH CHILDREN’S         This project has had a very stringent budget and SJ Higgins Group have
           INTERIM PROJECT           worked with the QS to eliminate significant cost risks. Examples of vale-
                                     adding include:

                                     Level 4 escape path
                                     A fire escape path was required on the 4th floor. This is a very difficult area
                                     to work in with very little access and directly above the ICU. SJ Higgins
                                     Group changed the up-stands from concrete to masonry to reduce cost and
                                     removed the screed manually to ensure that we kept noise to a minimum
                                     not to effect the operation of the ICU.

                                     Level 1 footing strengthening
                                     SJ Higgins Group re-engineered the footing design to drastically reduce
                                     the size of the penWetration in the ground floor of the hospital. This saved
                                     considerable time in the project programme. It also reduced the periods of
                                     noisy demolition work that effected various departments. It also reduced
                                     the large amount of soil that had to be removed from the hospital and such
                                     prevent any infection control issues.

                                     Level 2 under slung services
                                     The sewer pipes, medical gas pipes, electrical mains that fed the new works
                                     on level 3-5 came through the level 2 ceilings spaces. There were several
                                     clashes with existing services, concrete beams that prevented the services
                                     entering the building as designed. We investigated and surveyed the entire
                                     area and found ways of bringing the new services in without effecting the
                                     structure, floor layouts of both existing level 2 and the new level 3 works.
           PENOLA COLLEGE            Cost savings include alternative lift up tilt door, spandrel alternative frame
                                     selection and departure from specified lockers to builders preferred model.
           CENTRO TWEED HEADS        We proposed and subsequently installed above ground grease arrestor
           SHOPPING CENTRE           traps for trade waste drainage in lieu of 3 meter deep excavation and under-
           REFURBISHMENT             ground installation with a reinforced concrete lid, poured in-situ. This saved
                                     the Client in excess of $20,000 and a number of days in installation.