Page 27 - EOI_Wallace Bishop Retail Redevelopment
P. 27

INNOVATION AND VALUE ADDING


















           DANDENONG HOSPITAL        Works to External Facade
           AAU                       SJ Higgins provided forecast costs and scope of works to provide the
                                     required outcome within a budget for the client. Domestic Imaging Offices
                                     - SJ Higgins provided a plan and forecasted cost and scope of works to
                                     provide the required outcome within a budget for the client.

                                     Clashes with Existing Structure
                                      SJ Higgins provided design advise to rearrange a 5 bed room which
                                     looked to have lost a bed space due to clashes with an undocumented
                                     concrete column in the middle of the room. The room was redesigned as
                                     per SJ Higgins advise and the 5th bed was able to be achieved
           MAROONDAH HOSPITAL          ˃ Structural framing was value engineered during Stage 2 works to mitigate
                                      costs and save time which impacted several trades across the stage.
                                       ˃ Floor preparation and screed works to meet the design intent were
                                      value engineered substantially during Stage 2 Level 3 South, to mitigate
                                      additional costs as a result of existing conditions.
                                       ˃ Floor vinyl specification was substituted by an equivalent product to
                                      provide a cost saving.
                                       ˃ Numerous areas of the hospital’s existing facade were remediated during
                                      the project as additional scope utilising existing access equipment at no
                                      additional cost.
                                       ˃ A complete redesign of the lighting system was proposed to the design
                                      team early in the project lifecycle and accepted by all stakeholders.
                                       ˃ Substituted Hydraulic fixtures for the dilapidated areas provided the client
                                      savings on scope changes.
                                       ˃ Encapsulating asbestos sprayed concrete clips to provide a legislative
                                      approved condition for minimal cost impact.

           MASTERS STORE             Structural design changes were utilised to improve buildability.  Precast
           MORNINGTON                walls were upgraded to act as retaining walls and support suspended floor
                                     slab.
                                     Large 200CUM detention system under suspended floor slab was modified
                                     to allow back filling to act as lost formwork.
           ST MACARTAN’S PRIMARY     Detailed material reviews found several costs savings including alternative
           SCHOOL                    external cladding, alternative pergola framing timbers and alternative cavity
                                     sliding door tracks, which achieved substantial cost savings.
           LAKE VERMONT MINE         There were a number of design and construction methods which allowed
                                     SJ Higgins Group to reduce costs.
                                     The Concrete slabs were designed to allow the Ultra Class Haul Trucks to
                                     be jacked anywhere on the slabs and also allow tracked machinery to be
                                     driven over the concrete.  This was achieved by adding 50kg/m of steel
                                     fibre reinforcing into the concrete to minimise damage done by tracked
                                     machinery.  This resulted in not requiring Steel rails to be installed in the
                                     concrete slabs and then further reduced costs by working with our concrete
                                     batching plant to produce the concrete and deliver it so that the steel
                                     fibre was located only within the top half of the 425mm thick slabs.  This
                                     was achieved without the formation of cold joints by retarders and careful
                                     programming.  The structural steel design was also developed to ensure
                                     internal bracing and welded beam members were not required.  This was
                                     completed by using large struts external of the building to support the large
                                     building mass.
                                                                                                              27
   22   23   24   25   26   27   28   29   30   31   32