Installation




                             Termination Box Connection              GuardII+ Connection
                               Term Box #2, Pair 1 BΦ C2                      C2 8
                               Term Box #2, Pair 1 CΦ C1                      C1 9
                               Term Box #2, Pair 1 CΦ C2                      C2 9
                               Term Box #2, Pair 2 AΦ C1                     C1 10
                               Term Box #2, Pair 2 AΦ C2                     C2 10
                               Term Box #2, Pair 2 BΦ C1                     C1 11
                               Term Box #2, Pair 2 BΦ C2                     C2 11
                               Term Box #2, Pair 2 CΦ C1                     C1 12
                               Term Box #2, Pair 2 CΦ C2                     C2 12


              5.8.4.  6-Sensor SSC Connections
                        To connect a 6-sensor SSC PD card, make the connections shown below.  In addition to
                     the sensor connections, an SSC PD technology also requires an external synchronization
                     source.



















                                        Figure 5-11 Typical 6-Sensor SSC Termination



















                                       Figure 5-12 6-Sensor SSC PD Card Connections