Date: 12/08/2012
Subcontractor: ABC Plumbing, Inc. DBA ABC Inc.
ACI Project No.: 2122
Project Name: Pacific High School Modernization
RE: Subcontract Agreement
Enclosed, find two (2) copies of the Subcontract Agreement for the above referenced project. Please execute and return both copies
along with the following documents by 12/18/12 to ACI (Attention: James Yost). Do not make any modifications to the Subcontract
Agreements. Please provide the following:
1. Faithful Performance Bond and Payment Bond -– Required per Section 12 of this agreement: YES NO
2. Certificate of Insurance - Refer to Section 11 of this agreement. Angeles Contractor, Inc., must be additionally
insured. A Sample Insurance Certificate is enclosed for your reference.
3. Detailed Schedule of Value (SOV) - Per Phases.
4. Preliminary Construction Duration for your own scope of work- Per Phases. This is required to develop the
Master Construction Schedule if not provided by the owner already in the specification.
5. Public Contract Compliance Documents or Labor Compliance Program Documents, if required in Spec.
6. W-9 (Request for Taxpayer Identification Number).
7. Contact Information - Name, Phone #, and E-Mail Address of your Project Manager / Superintendent / Accounting.
8. Other:
Once these agreements have been fully executed, a copy will be returned to you.
Also, please be advised that the Pre-Construction Meeting will be held at ACI Main Office or Job Site at 20632 Main Street, San
Bernardino, CA 96033 on 12/20/12. Your representative is required to attend the meeting. If you have any question, please do not
hesitate to contact me at 714-443-3655.
Sincerely,
ANGELES CONTRACTOR, INC.
By: Walter Shirley
Senior Project Manager