Page 86 - FINAL Phillips 66 50 Year Book
P. 86

The newsletter also lifted the lid on a refinery procedure that’s somewhat
            mysterious to outsiders… the silence of shutdown.

            ‘When  the  plant  is  shut  down  there  is  sometimes  an  eerie  silence,
            without the usual steam and velocity noises you are used to. There’s
            also an air of vulnerability at the thought that the refinery isn’t earning
            anything and it’s your team’s responsibility to get things up and running
            again.’


            Project manager Peter Grout’s atmospheric description revealed what
            went on during that summer’s maintenance shutdown, when six main
            contractors and some 40 sub-contractors were on site to maintain and
            inspect the refinery. At its peak, the workforce – of electricians, riggers,
            fitters, scaffolders and specialist cleaning companies – was made up
            of 3,620 on days and 760 on nights, working 10 hour shifts, six days a
            week. The car park was transformed into the main contractor village for
            the 10 week long project.


            So, although the industrial noise may have disappeared, the site was
            anything but quiet. And despite its complexity the shutdown was one
            of the refinery’s safest ever, with no environmental violations. Some   The statistic show what sort of work goes on on-site:
            project work was  also  carried  out,  to improve  coke  throughput  and   • 384 control valves, 476 pressure relief valves and 87 electric motors
            quality, and fine-tuning to the No.3 Vacuum Unit.               removed and overhauled.
                                                                        • 1,512 equipment inspections.
                                                                        • 8,839 radiographs on welded pipelines.
            The statistics of shutdown are staggering. On this one alone, catering
            contractors Aramark dished up: 120,000 breakfasts; 30,000 lunches;   • 55 cranes on site.
            58,000 bottled and canned drinks; 10,000 nightshift meals; 31,000   • 565 extra mobile radios hired out for improved communications.
            sausages and burgers; and 52,000 portions of chips.         • 138 temporary generators.
                                                                        • 200 plus portable cabins for contractor changing and mess rooms.
             Far Right: Contractor Turnaround Compound.                 • More than 20 temporary toilet blocks.
   81   82   83   84   85   86   87   88   89   90   91