Page 5 - RoadCem Working Platforms for Piling Case Studies_Neat
P. 5

With safe access and easy set up,             Photos from the award
                                                      the piling installation was rapid
                                                      with no deflection and easy                   winning Clay Mills
                                                      predictable alignment.
                                                      Allowing completion in less than
                                                      half the scheduled allotted time
                                                      for the operation.








                                                       The unique visco elastic
                                                       properties of the RoadCem soil
                                                       mat, prevented cracking and
                                                       reduced breakaway around the
                                                       piles.
                                                       The increased dynamic
                                                       absorption also reduced bounce,
                                                       aiding pile alignment.










                                                       On a visit to the site during piling
                                                       we were asked to take a photo of
                                                       these piles that had been stored
                                                       on the edge of the mat, on just a
                                                       2 inch wooden strips.
                                                       The H&S officer from piling plant
                                                       operators was amazed that
                                                       despite the heavy weight of the
                                                       stacked piles the mat was
                                                       unmarked and no shearing at the
                                                       edge of the mat had occurred.