Page 106 - Civil Engineering Project Management, Fourth Edition
P. 106

The employer and his engineer
                                                                                               91
                          8.3 A note on alternative provisions of the
                               ECC conditions
                          Under the ECC conditions a project manager is appointed to administer the
                                                                                   1
                          contract and he has no duty to act independently or impartially. He represents
                          the employer, so acts for the employer who is committed by his manager’s
                          decisions. Consequently the employer has no right under the contract to take
                          a dispute with his manager to adjudication or arbitration. But if the contractor
                          disputes any action of the project manager, this comprises a dispute between the
                          contractor and the employer which can be taken to adjudication or arbitration.
                            Asupervisor on site (with assistants if need be) is also appointed to carry out
                          certain specified duties relating only to the quality of construction. He inspects
                          and tests the work (Clauses 40 and 41) and instructs the contractor to search for
                          and remedy defects (Clauses 42 and 43). He submits reports to the project man-
                          ager and the contractor. Where his appointment is separate from that of the
                          project manager, their respective responsibilities need to be carefully defined
                          and co-ordinated.
                            The project manager’s duties include many similar to those listed above
                          for the engineer under the ICE conditions, in particular under the ECC these
                          include:

                          • giving early warning of changes (Clause 16);
                          • resolving ambiguities in the documents (Clause 17);
                          • deciding and certifying completion (Clause 30);
                          • accepting or not accepting the contractor’s programme (Clause 31);
                          • instructing a suspension of work (Clause 34);
                          • certifying take over of the works (Clause 35);
                          • assessing and certifying payments due (Clauses 50 and 51);
                          • deciding on compensation events, asking for quotations from the contractor
                             for these and assessing any payment or time extension due (Clauses 60–65).
                          Further differences between the ECC conditions and ICE conditions are dealt
                          with in Sections 17.3, 17.8, 17.11 and 17.12.



                          8.4 Limitations to the engineer’s powers under
                               ICE conditions


                          Under the ICE conditions the engineer can only instruct a variation of the
                          works which is ‘in his opinion necessary for the completion of the works’, or
                          ‘desirable for the completion and/or improved functioning of the works’.
                          Thus the engineer cannot order matters which are, for instance, extraneous to

                          1 Although he has no duty to act impartially, he will in practice do so, to avoid a dispute arising which
                          the contractor takes to adjudication or arbitration.
   101   102   103   104   105   106   107   108   109   110   111