Page 107 - Civil Engineering Project Management, Fourth Edition
P. 107

Civil Engineering Project Management
                          92
                          the works or which add entirely new items; these are matters the engineer
                          must refer to the employer who will need to negotiate with the contractor his
                          agreement to undertake the addition (see Section 17.3).
                            Although the engineer is given a wide range of powers, he should not use
                          them without reference to the parties to the contract, either of whom may wish
                          to state his view on matters the engineer has to decide. The FIDIC conditions, for
                          instance (see Section 4.3), specifically call for such consultation by the engineer
                          as part of the procedure he must adopt before arriving at his decision.
                            However, if the employer wishes to restrict the engineer’s powers which
                          would otherwise be exercisable under the contract, the employer must state
                          in the tender documents the specific powers which the employer reserves for
                          himself. Both the ICE conditions Clause 2(1)(b), and the FIDIC 4th edition
                          conditions require this. But it is unwise for the employer to reserve too many
                          powers for himself, because this could affect the basis of contract and reduce
                          the benefit of having an independent engineer. Tenderers might then take a
                          different attitude towards the contract, since a tenderer may only offer his low-
                          est price if he is confident that an independent engineer will administer the
                          contract. Employers should also be aware that prior approving of matters such
                          as extension of time or claims may restrict their ability to dispute them later.
                            However an employer may sometimes wish to ensure that he is involved in
                          decisions likely to cause additional expenditure above some given limit, or
                          which alter significantly some aspect of the works. In practice, such restric-
                          tions are unlikely to detract from the engineer’s independent position because
                          the engineer should keep the employer advised of such matters and endeav-
                          our to agree with him what should be done. Most extra costs arise from hav-
                          ing to deal with unforeseen conditions which must necessarily be dealt with,
                          or from alterations required by the employer himself.
                            A different situation can arise if it becomes evident that the estimated final
                          cost of the contract is approaching or likely to exceed the contract sum. In that
                          case the engineer must forewarn the employer in good time, because an
                          employer such as a government or local government authority, may have no
                          authority to spend more than the contract sum, or may need to go through
                          a lengthy procedure to obtain sanction for any excess expenditure. In these
                          circumstances the employer may need to step in and negotiate with the con-
                          tractor a change to the works required, or perhaps deferment of construction
                          of part of the works to some later date.


                          8.5 The engineer’s duty to provide all necessary
                               drawings to the contractor


                          Under the ICE conditions the engineer has a duty to provide the contractor
                          with the drawings and further instructions needed to carry out the works. This
                          is additional to the tender drawings issued which do not need to show every
                          detail. The engineer must therefore watch construction progress to ensure any
   102   103   104   105   106   107   108   109   110   111   112