Page 179 - Civil Engineering Project Management, Fourth Edition
P. 179

The resident engineer’s office records
                                                                                              161
                            The question can be asked – need the RE keep such a stock register if the con-
                          tractor supplies the pipes and valves, etc.? The answer depends on the method
                          of payment to the contractor. If he is paid unit rates for ‘supply, lay and joint…’
                          pipes and valves, then it is not necessary for the RE to keep a stock record – but
                          the contractor will be wise to do so for the reasons given above. If, however,
                          the contractor is to obtain the pipes and valves from nominated sub-contractors
                          whose charges are reimbursed to the contractor, then the RE should set up the
                          stock-book to check that mismanagement of items and unnecessary wastage
                          does not occur.
                            Any materials left over on completion of the contract remain the property
                          of the employer if supplied by him. This is another reason why control via a
                          stock-book should be exercised by the RE, so that the employer does not get
                          returned to him a miscellany of cut pipes of little use to him, but as many
                          whole pipes and undamaged specials as possible.


                          13.13 Registers of test results


                          Test results on materials should normally be recorded on special forms to a
                          format supplied by the engineer. A file for each type of test should be kept on
                          site, copies of the tests being sent to the engineer. A general classification of
                          tests for filing would be as under.

                          • Borehole logs, trial pit results, etc.
                          • Foundation material tests: grading curves; sample tests; analyses, etc.
                          • Earthwork tests: Proctor compaction tests; in-situ density tests; etc.
                          • Concrete tests: aggregate gradings and tests; cement tests; cube and beam
                             tests, etc.
                          • Pipeline tests.
                          • Miscellaneous tests.
                          • Other manufacturer’s tests.
                          Files should be fronted by a register of all tests taken. The particulars on the
                          register must show where the sample is taken from, the date taken, date tested,
                          and nature of test. Reference numbers for all samples must be given, and indeli-
                          bly written on the sample packaging. Simple errors in labelling concrete test
                          cubes, for instance, can lead to time-consuming, expensive and unnecessary
                          alarms.
                            The position of all foundation or earthwork investigations, inspections,
                          probes, samples, etc. should be marked on a plan. It is essential to keep a
                          second up-dated copy of this plan since loss of it can greatly reduce the value
                          of such investigations.
                            On many civil engineering projects equipment installed of various kinds
                          may need to undergo performance tests, some of which may be extensive last-
                          ing several weeks. Also logs of various observations of the performance of the
                          works may be needed, such as movements of a dam during filling or settlement
   174   175   176   177   178   179   180   181   182   183   184