Page 183 - Civil Engineering Project Management, Fourth Edition
P. 183

14

                                            Programme and

                                             progress charts













                          14.1 Responsibilities for programming the
                                construction


                          The contractor is responsible for producing a programme for construction
                          for the job, though he must comply with any special requirements laid down
                          in the contract documents. Under the ICE conditions the contractor must sub-
                          mit his proposed programme within 21 days of being awarded the contract
                          (Clause 14(1)). Within a further period of 21 days (see Section 9.5 Item 4), the
                          engineer must accept or reject it, or call for more information on it; if not, he is
                          deemed to have accepted it (Clause 14(2)). If the engineer calls for more infor-
                          mation, the same time limits are repeated.
                            The programme for construction may therefore have been agreed before
                          the resident engineer goes to site. But the resident engineer needs to check
                          what it requires with respect to (1) the provision of further drawings and
                          information to the contractor, and (2) the provision of any materials or services
                          to be supplied by the employer under separate contracts he has entered into,
                          or which are to be obtained by the contractor from nominated suppliers.
                            The delivery times for nominated suppliers and sub-contractors should
                          have been quoted in the main civil engineering contract, requiring the con-
                          tractor to allow for them when drawing up his programme. It is prudent to
                          add ‘margins of safety’ to the delivery times quoted in the contract because
                          (a) the contractor can only place orders with them after he is awarded the
                          contract, and (b) the nominated firms might not deliver on their promised
                          time, causing a delay to the contractor’s programme enabling him to claim
                          for delay.
                            Hence the resident engineer should check the current delivery times
                          quoted by nominated firms and advise the contractor of the latest times he
                          must place orders.
   178   179   180   181   182   183   184   185   186   187   188