Page 184 - Civil Engineering Project Management, Fourth Edition
P. 184

Civil Engineering Project Management
                          166
                          14.2 Difficulties with nominated sub-contractors
                                or suppliers
                          The use of nominated sub-contractors or nominated suppliers can cause
                          many problems because the engineer cannot interfere in the terms of the sub-
                          contract (see Section 15.8). The sub-contractor or supplier may refuse the sub-
                          contract because of disagreement with the contractor on liability for damages
                          (see Section 7.8), trade discount and terms of payment, or some extra charge the
                          contractor wants to make for services he provides. Sometimes a sub-contractor
                          refuses to accept an order from the contractor for reasons he will not disclose –
                          usually due to some past experience with the contractor. Although some prob-
                          lems can be overcome by careful detailing of all necessary provisions in the
                          specification, there is never any certainty the sub-contract will be signed. If
                          not signed the purpose of nomination is frustrated, and re-nomination may be
                          necessary causing the programme to be disrupted.
                            To avoid the problems of nomination the specification can specify the work
                          required and leave the choice of sub-contractor to the contractor; with the
                          proviso that the sub-contractor must be approved by the engineer. Nominated
                          suppliers can also be avoided by specifying items, where possible – ‘As Messrs.
                          XYZ’s product or similar’– leaving the onus on the contractor to choose his
                          source of supplier.
                            But this is not always possible when, for instance, the employer wishes to
                          use facing bricks available from only one supplier. An alternative then is for
                          the employer to place the order for the bricks direct with the supplier, making
                          arrangements for their offloading and stacking; with the engineer denoting
                          in the contract for construction where the contractor is to find such bricks, etc.
                          The resident engineer needs to ensure all such arrangements are being made
                          in due time to avoid delay to the contractor.
                            Fortunately many small items to be supplied by nominated suppliers are
                          not crucial to the contractor’s programme, or not required until the finishing
                          stages of the contract. These usually do not give rise to many problems, and
                          the contractor can be encouraged to order them in good time by the engineer
                          certifying part payment of their value under ‘materials on site’.



                          14.3 The role of the resident engineer


                          The resident engineer should contact separate and nominated sub-contractors
                          or suppliers, advising them construction has started, getting them to confirm
                          their delivery times. He should also make sure that all technical queries are
                          settled. Where suppliers have to manufacture substantial equipment, he will
                          check their progress, and may visit them to make personal contact. He will
                          do everything possible to prevent any delays occurring and, if he sees some
                          delay is unavoidable, he will inform the engineer and make suggestions as to
   179   180   181   182   183   184   185   186   187   188   189