Page 189 - Civil Engineering Project Management, Fourth Edition
P. 189

Civil Engineering Project Management
                          170
                          concreting, brickwork quantities etc. together. However, if there are only a
                          few structures to deal with, bar charts for each will be practicable.
                            An alternative is to use a computer to display bar charts at several levels
                          of detail. For resource planning and material ordering purposes the detailed
                          operations required for each structure can be shown on one chart, and these
                          can be summarized into one bar on another bar chart, which in turn can be
                          used to represent progress on the project as a whole. Critical linkages between
                          operations can be fed into the program as for network diagrams (see Section
                          14.5 ), and the resulting critical paths and ‘floats’ can be derived. Adjustment
                          to a detailed bar chart – perhaps due to some delay or extra work – is auto-
                          matically reflected in the overall summary bar chart display. Of course the
                          operation of such software requires investment in the time and the use of skilled
                          operators, so the cost may only be justified for a large complicated project.
                            Another form of progress chart is to mark up the cumulative value of work
                          done on a graph as illustrated in Fig. 14.3. However, to ensure that such a chart











































                          Fig. 14.3. Financial progress chart. The forecast line shows that the contract is likely to
                          be completed about 3 months late at £0.3 million excess cost
   184   185   186   187   188   189   190   191   192   193   194